City of Cushing: Wastewater Treatment Plant Upgrades

City of Cushing: Wastewater Treatment Plant Upgrades
October 2015


Project Highlights

Project Manager Jeremy Buechter, P.E.
Location City of Cushing
Role Primary
Type Wastewater
Completed October 2015
Final Construction Cost $765,000

Project Description

SPI assisted in the procurement of multiple funding sources from CDBG and TWDB for the City of Cushing for design and construction. This funding was used towards necessary upgrades to the existing wastewater treatment facility to bring the discharge effluent back into compliance. These improvements were designed by SPI and included rehabilitation of the existing imhoff tank, a new Blue Frog Aeration System, new gas chlorine disinfection system with contact chamber, and gravity sewer line/manhole replacement. Construction was completed in October 2015 at a cost of $765,000.


Contact Schaumburg & Polk, Inc.

For more information about the engineering services we provide, please feel free to call the location closest to you or use the contact form on our site. We'll be glad to help answer any questions you have or discuss the specific needs your infrastructure project. Thank you for visiting our site, and we look forward to hearing from you.